Underfloor System - insulation panel and PEX pipe

Laying and testing

 
In order to start the laying of a radiant system it is necessary that the frames of the external windows and the internal doors have been already laid, the plasters realized and the electrical systems ended.

For the laying of the electrical and sanitary distribution systems you can choose between two solutions: laying the systems on the slab and then doing a metallic electro-welding net, or leaving 30 cm along the internal walls where the systems will run.